Fact check
“The New Jersey Department of Environmental Protection fined the company over the fleet of generators but did not disclose how long the generators had been operating nor how much air pollution they had released into the surrounding community over the past year.”
Reasoning
The Guardian articles report that the New Jersey Department of Environmental Protection fined the datacenter for unpermitted generators and explicitly note that the agency did not disclose how long the generators had been operating nor the total amount of air pollution released. The articles also provide an estimate of emissions (about 140 tons of NOx) but indicate that the agency itself did not release these figures.
On confidence: Multiple primary sources from The Guardian directly state that the NJDEP fined the company and did not disclose the operating duration or total emissions.
Important context
The claim concerns the NJDEP's nondisclosure of operational duration and emission totals. The evidence confirms the fine and the lack of disclosure, while also providing external estimates of emissions.
Evidence
Supporting (2)
- Tier 1 — Primary sourceUS datacenter discharged large amounts of pollution for almost a year with no permits | Pollution | The Guardian
how long the generators had been operating nor how much air pollution they had released into the surrounding community over the past year. Floodlight sent technical data about the generators – obtained through public records requests – to…
- Tier 1 — Primary sourceUS datacenter discharged large amounts of pollution for almost a year with no permits | Pollution | The Guardian
08.00 EDT Share Prefer the Guardian on Google DataOne, the Microsoft-linked New Jersey datacenter recently hit with a $1m fine for running unpermitted generators, emitted large amounts of health-harming air pollution for nearly a year…
Contradicting (2)
- Tier 1 — Primary sourceNew Jersey datacenter fined $1.1m after visual investigation showed dozens of unpermitted generators | Datacenters – US | The Guardian
Microsoft-linked AI datacenter, has stirred controversy since it broke ground in 2025 due to consistent noise complaints, unpermitted construction and a combative zoning process. The site lies roughly 40 miles (64km) outside Philadelphia…
- Tier 1 — Primary sourceNew Jersey datacenter fined $1.1m after visual investigation showed dozens of unpermitted generators | Datacenters – US | The Guardian
record setting for the DEP, $1m does not affect companies like DataOne,” said Matt Williams of Sustain SJ, an environmental advocacy group. He added that “ceasing operations immediately would be the appropriate response”. A social media…
Contextual (1)
- Tier 1 — Primary sourceUS datacenter discharged large amounts of pollution for almost a year with no permits | Pollution | The Guardian
Both concluded that at full use, DataOne’s fleet could emit more than 1,500 tons of NOx per year. That is nearly twice the amount that the Linden Cogeneration gas-fired power plant, New Jersey’s largest NOx emitter, is allowed to emit.…
Limitations
All evidence comes from a single news outlet (The Guardian). No direct NJDEP statements or independent government documents were provided to corroborate the nondisclosure claim beyond the reporting. No independent origin corroborated this claim, so it cannot be verified and confidence cannot be high.
- Last verified:
- Oct 1, 2026, 8:47 AM CDT
- Pipeline:
- 2.1.0
- Claim type:
- Factual
Where this claim appeared
US datacenter discharged large amounts of pollution for almost a year with no permitsThe Guardian · Evan Simon of Floodlight